Takeoff grid
Contains the items in the selected assembly. Before generating the assembly into the spreadsheet, you can substitute,
add, or delete items, adjust labor and equipment productivity, and specify
the quantities, locations, labor productivity and price tables, and work
breakdown structures.
Tips:
- When you review an assembly,
a gray background indicates the standard database used to take off the assembly
is not open. To change an assembly pass, open the standard database that was used
to take off the assembly.
- A red triangle in the upper
right corner of the row header means that the item has a pending adjustment.
- You can select one or more
Quantity cells and choose a command from the shortcut menu to specify
quantities using the calculator, ePlan Takeoff, or a formula.
- Click [Notes]
to open the Notes window where you can enter or view information about
a particular assembly. A paper clip on the Notes button means there is
already a note attached to the assembly.
- Click [Attachment]
to display the help topic, if available, for the selected assembly.
- Sage Estimating automatically
generates a pass to an assembly when you change the quantity of an item
in the takeoff grid. A pass note identifies the item and its original
amount.
- Labor productivity and material
price tables are available only if a standard database is open and you have set
it up to use productivity or price tables. If no tables have been selected, Sage Estimating prefills the
values specified in Estimating Information ().