Working with standard databases > Building and modifying a standard database > Work breakdown structure values > Changing an existing work breakdown structure (WBS)
Changing an existing work breakdown structure (WBS)
-
Open the Estimate Settings window.
- On the ribbon, from the Views group on the Home tab,
click Settings.
- In classic view, click Takeoff > Estimate Settings.
- In the Estimate Settings window, click the WBS tab .
- Select the source.
To change a WBS
code in the current estimate, select Estimate.
To change a WBS
code in the standard database, select Database.
Note: Changing WBS codes in the standard database
does not affect existing estimates.
- Change selected WBS codes as necessary.
- To delete a WBS
code, select the row, and then click [Delete].
- To remove all references
to the WBS codes and their associated values from items, addons, spreadsheet
sequences, and assemblies, click [Clear
All]
- When you finish making
changes, click [OK] to save them.
- Click [Close].
Tip: You
can also change standard database WBS codes in the Database Settings window from
the Data tab (Database menu in classic view).