Example: A crew consisting of the following resources:
| Quantity | Resource | Rate |
|---|---|---|
|
2 |
Laborer1 |
7.00/hour |
|
1 |
Laborer2 |
10.00/hour |
Could have either of the following prices based on the selected crew pricing method.
| Average cost per person | Total cost of crew |
|---|---|
|
8.00 per hour (24.00 / 3) |
24.00 per hour (7.00 + 7.00 + 10.00) |