Example: A crew consisting of the following resources:

Quantity Resource Rate

2

Laborer1

7.00/hour

1

Laborer2

10.00/hour

Could have either of the following prices based on the selected crew pricing method.

Average cost per person Total cost of crew

8.00 per hour (24.00 / 3)

24.00 per hour (7.00 + 7.00 + 10.00)