Amount
Displays the extended cost (bid quantity x unit cost) of
the entire bid. When you choose the subcontractor to be used, Sage Estimating
puts this value into the Sub Amount column for the item from which you
opened the bid grid. Other items included in the bid have an asterisk
(*) as the sub amount.
Tips:
- To see a pop-up window showing
the difference between a subcontractor's bid amount and your self-perform
amount, point to the Amount cell for that subcontractor.
- Changing a bid amount recalculates
the unit cost.
- To restore items in the spreadsheet
to their previous category amounts, double-click the header of the self-perform
row.
- You cannot edit the self-perform
row.