Picking subcontractors and entering their quotes
Before you begin
- Click the Phase/Item tab
to display the spreadsheet in phase/item order. While you don't have to
display the spreadsheet in this order, it's typically the most convenient
order to use for entering material quotes.
Example
- Make the first four spreadsheet
columns non-scrolling so you can easily identify the items after you scroll
over to the Material category columns. How?
To pick subcontractors and enter their quotes:
- Scroll the spreadsheet
until the Sub columns display.
- Enter the subcontractor's
quote in the
or
cell for the appropriate item.
- Enter the subcontractor's
name in the corresponding Sub Name cell.
Right-click on
the cell and select List Address Book Subcontractors for a list of companies in the Address Book database that are available for use as subcontractors.
If necessary, you can set up a new subcontractor from
the Sub Name column. How?
- Repeat steps 1-3 until
you have entered all subcontractor quotes.
Tips:
- Did you enter a lump amount
that applies to multiple items in the estimate? For each item covered
by the lump amount, enter an * (asterisk) in the Sub Amount cell. The * indicates that the item is covered by monetary amounts located elsewhere
in the estimate.
- Sage Estimating places an * in
the following cells to indicate that the item is covered by monetary amounts
located elsewhere in the estimate: Sub Productivity, Sub Cost/Unit, Sub
Quantity, and Sub Price.
- Another
way to enter bids from subcontractors is using the bid grid. How?