Setting up in Sage 300 Construction and Real Estate Job Cost

You need to set up the following information in the Job Cost application:

Tip: Sage recommends using the same coding scheme for phases in Sage Estimating and cost codes in Job Cost. Although Sage Estimating can handle different coding, using the same scheme minimizes data entry in Sage Estimating. If you want, you can import Job Cost data directly into your Sage Estimating standard database. When you set up your standard database, select Sage 300 Construction and Real Estate as the Job cost interface type.

If the two applications have different coding, you will have to set up a job cost phase for each phase in Sage Estimating. Keep in mind that multiple phases can reference the same Job Cost code.