Default Crew Pricing

Choose how to calculate the labor/equipment crew price for items with these generic time-based order units: Hour, Day, Week, Month.

  • Average cost per person uses the average cost of all members of the crew to calculate labor and equipment costs.
  • Total cost of crew calculates the pricing based on the total cost of the crew.

For example, a crew consists of the following resources:

Quantity Resource Rate

2

Laborer1

7.00/hour

1

Laborer2

10.00/hour

This crew could have either of the following prices, depending on the selected crew pricing method.

  • Average cost per person: 8.00 per hour (24.00 / 3)

  • Total cost of crew: 24.00 per hour (7.00 + 7.00 + 10.00)