Example: A crew consisting of the following resources:
Quantity | Resource | Rate |
---|---|---|
2 |
Laborer1 |
7.00/hour |
1 |
Laborer2 |
10.00/hour |
Could have either of the following prices, depending on the selected crew pricing method.
-
Average cost per person: 8.00 per hour (24.00 / 3)
-
Total cost of crew: 24.00 per hour (7.00 + 7.00 + 10.00)