Model Setup Form

Planning a model is a form of takeoff because you are selecting all the labor and material required for a model instead of an estimate. For example, a garage model might include assemblies for a slab, stud walls, and roof as well as door and siding items.

Fill out one copy of this form for each model you plan to set up.

Model (code)  Use up to 20 characters

                                                                                        

Group Select the box if this is a group model.

q

Description Use up to 70 characters.

 

Notes

 

 

 

 

 

 

 

 

 

 

Questions
Question 
Question 
Description 
Default 
Calculation
Question
Type (Text, Numeric, Yes/No)

Example:

Show Picture

Would you like to see a picture of the building type?   Yes/No
       
       
       
       
       
       
       

 

Assemblies

Assembly 
Assembly 
Description 
Assembly
Unit 
Assembly
Calculation

Example:

0301a

Foundation – Footing NoRbar Some Choice cy aCY Concrete 0301
       
       
       
       
       
       
       

 

Items
Phase 
code
Item
Code
Item 
Description 
Takeoff
Unit 

Formula

Example:

2315.021

20 Excavate Footing By Machine cy CY L x W x D'/27
         
         
         
         
         
         
         
         
         
         
         
         
         

Model notes