Export budget to job cost wizard: Step 3

In this step, you can include a phase for the budget in Sage 100 Contractor. To include a phase, you must specify the sort level in the estimate that corresponds to the phase in Sage 100 Contractor.

To export a budget – Step 3:

  1. (Optional) Select the Include an estimate sort level to be used as a Sage 100 Contractor Phase check box, as needed.

    If you select the check box, a list box containing all estimate sort levels becomes available.

  2. If you selected the check box, select a sort level from the list box.

  3. Click [Next].