Example: Suppose a job includes 1000 square feet of slab, and you think overtime is needed to complete about 200 square feet of that total. You would need to take off the slab item twice as shown below.
Item | Takeoff quantity | Rate table |
---|---|---|
Slab on Grade |
800 sqft |
Regular Time |
Slab on Grade |
200 sqft |
Overtime |