Example: Suppose a job includes 1000 square feet of slab, and you think overtime is needed to complete about 200 square feet of that total. You would need to take off the slab item twice as shown below.

Item Takeoff quantity Rate table

Slab on Grade

800 sqft

Regular Time

Slab on Grade

200 sqft

Overtime