Type of unit
Click
to choose a type that specifies
whether a unit is time-based. Sage Estimating (SQL) calculates the labor and equipment
hours for all items that have a time-based order unit in the per field
of the Edit Items window.
- None: non time-based unit
- Hour, Day, Week, Month: generic time-based units
- Person Hour, Person Day, Person Week, Person Month: man-based units
-
Crew hour, Crew day, Crew week, Crew month: crew-based units
Note: This feature is available only if you have a license to use Crews.
You open the Edit Items window in one of the following ways:
On the ribbon, from the group on the Data tab, click .
Tips:
- There must be time-based units of measure if you want Sage Estimating (SQL) to calculate total hours and crew prices.
- In the unit list, a small
clock symbol
identifies the time-based units.