Working with standard databases > Building and modifying a standard database > Crews > Changing an existing rate table
Learn more

Changing an existing crew

Crew overview

Setting up a new crew

Testing crew amounts

Setting up a rate table for overtime

Setting up a new rate table for crew pricing

Changing an existing rate table

  1. Open the Database Rate Table window in one of the following ways:

    • On the ribbon, from the Crews group on the Data tab, click Rate Tables.
    • In classic view, select Database menu > CrewsRate Tables.
    • From a crew or rate table, right-click a cell in the Resource column, and then select Edit Rate Table from the shortcut menu.
  2. Select the rate table you want to change.
  3. The source option indicates where the rate table showing in the window is stored. If you opened the window from the spreadsheet, you can choose to change a rate table in either the estimate or the standard database.
  4. You can click image\list.gif to choose from a list of existing rate tables in either the estimate or standard database, or scroll through the rate tables using [<<] and [>>].
  5. Make changes as needed.
    • To rename the rate table, click [Rename], and then enter the new name in the Rate table field.
    • To change a resource rate, click the cell, and then enter the new rate.
    • To add, delete, or modify resources in the rate table, move the cursor to the resource name or description cell and right-click to display your options. How?
    • To change the heading for a benefit/other cost column, right-click the column heading, right-click, and then select Change Benefit Column from the shortcut menu. Enter the new heading in the Changing Benefit Column window, and then click [OK].
    • To change how the rate for a benefit/other cost column is calculated, right-click the column heading, and then select the desired option from the shortcut menu: Amount per Unit or Percent of Base Rate.

    For more information, click image\windhlp.gif on the title bar of the window and then click a field or button.

  6. When you finish changing the rate table, click [OK] to save it.
  7. Change other rate tables in the same manner. When you finish, click [Close].

Tips: